Perleberg Solarpark

Perleberg

SUNNY CENTRAL 760CP

Maximum reliability with Sunny Central 760CP

In record time of just two and a half months of construction the Perleberg solar park has been completed on the grounds of a former military airport in Brandenburg. On an area of 16253 hectares 144144 modules manufactured by Yingli, 39 Sunny Central 760CP inverters and 500 kilometres cable were used.

The solar power plant achieves a nominal capacity of 35 MWp and it is expected to produce about 33 million kilowatt hours of environmentally friendly solar power annually. So it can cover the need of 9300 three-person households and save then approximately 32000 tons of CO2. Due to the solar park’s high capacity, the company also built a separate expandable 110 kV transformer station, which serves to connect the solar park to the grid.

Commissioning

  • June 2012

Nominal power

  • 35 MWp

Modules

  • 1144144 modules from Yingli
    YL235P-29b & YL240P-29b

Inverters

  • 39 Sunny Central 760CP

Contact

SMA Australia Pty Ltd
Level 1, 213 Miller Street
North Sydney NSW 2060
Australia

PO Box 645,
North Ryde BC, NSW 1670,
Australia

Tel. +61 (02) 9491 4200
Fax +61 (02) 9491 4290
Freecall 1800 SMA AUS

info@SMA-Australia.com.au
www.SMA-Australia.com.au